 | |  | |  | |  | |  | | Pipe lengths strung out on right of way ready for welding |
|
 | |  | |  | |  | |  | | Welding crew welding previously strung pipes in to a length of pipeline |
|
 | |  | |  | |  | |  | | FBE (fusion bonded epoxy) coating of welded joints, after NDT acceptance |
|
 | |  | |  | |  | |  | | Profiled ditch excavation, ready for pipeline lowering-in |
|
 | |  | |  | |  | |  | | Twin pipeline fabrication with pull head ready for pullback through horizontal directional drill (HDD) road crossing |
|
 | |  | |  | |  | |  | | Pipeline route in to plant |
|
 | |  | |  | |  | |  | | Pipeline lower and lay after welding and coating |
|
 | |  | |  | |  | |  | | Pipeline lower and lay - note flexability of steel pipeline when in long lenghts |
|
 | |  | |  | |  | |  | | Pipeline right of way after topsoil strip |
|
 | |  | |  | |  | |  | | Pipeline string over river in readiness for HDD pull back under adjacent river |
|
 | |  | |  | |  | |  | | Excavate to locate end of HDD road crossing pipe for tie-in |
|
 | |  | |  | |  | |  | | Right of way with twin pipeline ready for road crossing and lower and lay. |
|
 | |  | |  | |  | |  | | Preparing for HDD river crossing |
|
 | |  | |  | |  | |  | | Post pipeline construction underfield drainage installation - chain trench flex pipe with permeable backfill |
|
 | |  | |  | |  | |  | | Similtaneous well site drilling and pile driving for prefabbed module installation |
|
 | |  | |  | |  | |  | | Factory fabricated header and processing module - ready for shipping to site |
|
|
|
|